Showing posts with label Building. Show all posts
Showing posts with label Building. Show all posts

Friday, February 13, 2015

One week!


We have sod!  It is like the icing on the cake to our beautiful home.  I absolutely LOVE how everything has come together.  While I was worried about the colors and trim, it really has come together nicely.   I didn’t get to go in today, but there were a lot of people doing work.  From what it looked like, there was a man power washing the exterior, someone painting, and someone cleaning.  They are really trying to get our house ready!  I can’t wait to see everything on Monday!
 

I figured that since we were in the end of the process that I would look to see if we passed our final county inspection and we didn’t.  Not sure why it was submitted knowing that the house was not 100% complete.  When we walked through for our security meeting, there were some things that we noticed…..for example, the back door still didn’t have a deadbolt, which was one of the reasons for the failed inspection.   I know the house will be 100% before we move in, but it’s still disappointing to see that it failed due to little details that haven’t been taken care of.  

Speaking of inspections, we have our personal inspection scheduled for Tuesday and should have his findings that evening.   I know that he will do a thorough job and I hope that all of the contractors have done the same.  He told us from the beginning that this is where he finds issues….with the finishes and workmanship of the various contractors that put together the finished product.  

Speaking of finishes, I hope that the painters have fixed some of the sloppy work I’ve seen (hopefully that’s what they were doing today).   I have learned a lot from reading from others experiences, and I know to go over our house in great detail and to always speak up if we feel something isn’t right.  We will point out any and everything we see that we feel is not done correctly.  While this might not be a big investment to some, it is to us and we expect it to be done right.  It’s not personal, it’s business.

Thursday, February 12, 2015

8 days!!!

Normally after I leave work, I drive by the house to see if there is something new.  Today I needed to run errands for the kiddos Valentine’s parties ….As soon as I parked at Target, my PM called.  He addressed a couple of things I emailed him about.  I asked him about the sod and plants since we are about to hit a cold streak (probably followed by 80 degree weather….that’s Virginia for you).  He told me they were going in today!  I was totally shocked because I really didn’t expect to have anything.  So after I got off the phone with him, I called my hubby and asked him to swing by to get some pictures.

In our current house, the previous owner planted flowers and they come back every year, so all the work was done for me!  I do think I will make an attempt to ensure our yard looks nice and will plant some of my own flowers to enhance what has been done, but I have no clue when it comes to things green.  I asked the PM if our sod and plants would die especially with a chance for snow next week.  He said they would be fine, so here’s to hoping we have nice green grass and beautiful plants in the spring. 

We also got our stair/porch railings today.  They look very nice and I am EXTREMELY happy to see them!

Our PM told me they are doing the final finishes to make our house perfect! 

Here are some pictures of the yard and the rails.  I will be back tomorrow to see the sod!
 

 

Wednesday, February 11, 2015

9 more days!

We stopped by the house today to meet with a representative for our security system.  I'm pretty excited about that, but even more excited about what's in the house.....APPLIANCES and CARPET!  The next time we are in the house it should be almost complete.  

I'm guessing we will be waiting for warmer weather before we can get our sod, tree, and other plants....

It also looks like three other houses on our street will begin soon!  It's nice to see our community filling up.

Here are a few pictures from today....



 
 

 




Wednesday, January 28, 2015

Week 10


23 more days!  This week has been exciting.  I drove by earlier this week and there were boxes in the garage, so I took a peek (and I didn't go in, lol)!  Doors and cabinets! YAY!
 

 
Our deck went up this week.  I think at some point we will make it bigger, but it will do for now.  It’s definitely 100 times better than some things I’ve seen.
 

 
 

 
Here is our kitchen!  It’s all coming together.  I love the cabinets (maple cognac).  I think they look great.  So much space for all of my wine glasses....and other things that go in the kitchen.  Can’t wait to see how everything looks with our granite and appliances. 


 

 
We also have paint!  I’m so glad they don’t paint the walls white.  We don’t plan on painting until after our 10-month, so I'm glad it's a nice beige color.  I know a lot of people paint as soon as they move in, but I'm too nervous!  I already hate painting enough as it is, and I’m not interested in doing any touch ups due to nail pops, cracks, or other house settling stuff. 
 
 
Oh and we have a garage door and 2 out of 3 columns! One was cracked, so it's on the way!  I absolutely love this elevation.  
 
So what's next?  Driveway and walkway, bathroom tile, plumbing and lighting, granite, and I'm sure a lot more stuff that I can't remember.  I feel like a kid on Christmas morning! 

Wednesday, January 21, 2015

Early Week 9.....They are watching us!


Ryan Homes that is!  Yup, they read our blogs.   Am I the only one who didn’t realize this?!! LOL! Guess that was really naïve of me.
How did I find this out?  My PM….in a meeting we had today.  I greatly appreciate my PM calling me to have a meeting after my request and after he read my blog.  While my Week 8 post wasn’t the happiest post, it was honest and how I felt.  After our meeting today, I do feel better.  He explained the water on the floor….a long explanation but a plumber came out to make sure there were no leaks.  He explained that wood that looked all crazy on the porch….they use that wood for nailing the vinyl stuff.   He explained all the workings of drywall and let us walk in the house to take a look.  We also discussed the trim above and around the windows….hopefully they can remain white.  It just looks SOOOOO much better.   

I’m not happy that I’ve been banned from the house without our PM.  I hate that policy.  I really do think that at this point in construction we should be able to visit our sites as long as no one is working.  While I do understand it’s a liability issue, it does put a damper on the excitement of building a new home.   It’s my house that we are building, but it’s not MY house.

So what’s coming up?  Garage, columns, drive way, and paint.

We are still set for a closing date of February 20th!  Exactly 30 days away!  Wow time has flown by.  It seems like yesterday that I was driving by our empty lot wondering when they were going to finally start!
Here are some pictures of our walk thru today. 

Dining room and living room

 
Family Room
 
 
Kitchen
 
 
Morning room

 
Bedroom

 
Master

 
Bedroom



Friday, January 16, 2015

Week 8


This week was a busy week for our Naples.  There is a lot to talk about so this post will be LONG…..

After our pre-drywall meeting our PM told us the following time line for this week:  Insulation would go in on Saturday and siding and drywall would go in on Monday.  He also said the concrete in our garage would go in at some point this week. 

Since a lot of things will be happening to the inside of our house I told our PM that I wanted to start meeting weekly to see the progress.  Our PM told us at our pre-construction meeting that we were never to enter the house without him.  We honestly have followed his instructions and stayed out of the house.   Since my husband and I both work, I told our PM that we would not be able to meet until 4:00pm or later for our meetings.  Our PM wasn’t too excited about this and FINALLY gave us permission to go into the house after hours and on the weekends.  Note that I have taken full advantage of his offer!

So on Monday, I went to the house to see what was going on!  Insulation had been installed.  There was one minor problem….that leak that I talked about last week was still there.  I brought it up to our PM and he basically said that everything will be perfect before we move in.  No drywall.


 

Tuesday, I drove by the house and they had started working on the siding!  They had completed the back and sides of the house.  They work really fast! Still no drywall. 
 
Here are some cell phone pictures....

 
 

We had a snow day on Wednesday so I didn’t stop by the house.

Thursday they had started putting the siding on the front of the house.  The concrete for the garage had also been poured.  It all looks really nice.  Since no one was working, I decided to take a little tour of the house.  Our drywall had been delivered and was sitting on the floor in all of the rooms.  Now, back to that leak….you know the one in the kitchen???  Well someone thought it would be a good idea to put our drywall on that leak and now water was leaking on the drywall.  I also noted another spot in the kitchen where water was leaking from an above pipe.  As I was leaving, I noticed something going on with some of the wood in the roof of our porch.  I took pictures of the leaks and the porch and sent them to our PM…I’m documenting everything.  There is no way you will say I didn’t tell you or that you didn’t know! 

 
 
Here is the first leak and drywall
 
2nd leak:
 
 
 
 
Here is the porch thing I was talking about....what's the deal with that separated wood by the recessed light? 

 
 
Well here we are today….Friday!!  I have played phone tag all day with my PM and have sent him another email, to which I expect no response and I’m sure I won’t get a phone call until Monday at this point (did he forget about that little survey at the end of this experience?).  Our siding is done and it looks really nice.  I am pleased with mostly everything.  I just really wish Ryan Homes would do something better than the tiny samples they give you to pick out colors for an entire house!  Now that we can see the colors on a much larger scale, we actually like the white trim that is currently on the house.  We originally picked beige trim.  We think it will be too much beige in the end if they paint everything beige.  Since we were at the house we visited our SR at the model and he basically told us since our garage door is beige that the trim has to be beige.  He also said that after we close we can paint it any color since we don’t technically have an HOA (another post for another day).   So my question is this….if we can paint it after we close, why can’t you just keep it white like we want??!?!?!?  Well I emailed our PM again….and of course you know how that goes. 

Here is the siding with some white trim:







 So let’s rewind to earlier today….I was thinking about the house and wondering why drywall hadn’t gone up.  I remember my PM stating that there were some inspections that were supposed to happen this week and then a light bulb went off!  We must have failed an inspection L

After some research on my counties inspection website, I found out why we had a delay.  They failed the counties framing inspection.  This is disappointing for a couple of reasons.  1) Our PM never said anything about this failed inspection 2) Our personal inspection happened minutes before the counties inspection and the only thing our inspector noted was some water under the house.  Now I know our personal inspector might not check for the same things as the county inspector, but it is still disappointing.   They finally passed the framing inspection on Wednesday….the drywall was delivered on Thursday….and WE FINALLY HAVE DRYWALL TODAY!
 
Living room looking into dining room

Family Room
 
Kitchen


Morning Room
 
 

I’ve been reading RH blogs since before we signed our contract in September and there is one complaint that is pretty consistent amongst a lot of bloggers…..the quality of the drywall job is pretty bad.  I know nothing about drywall and the process, but I did note some things when I walked through our house this afternoon.  There are several places where the drywall just doesn’t look good.  I know we are in the beginning phases and there are several more steps, but I’m starting to wonder if we will be another blog that has drywall issues.  Should there be gaps in the drywall?  I know they use mud and tape to make it smooth and look seamless, but won’t gaps show as the house is settling?  This is another item added to the list of topics for our PM. 
Here are some pictures of what I'm talking about....




 

Remember that wood on the porch roof?  Well this was put up today, so I guess I’ll never know if it was actually fixed. 
 

Oh, in one of my many emails to our PM I asked if our closing date would be pushed back since drywall was delayed.  In a voicemail he said that we are still set for February 20th.   Is that date even possible at this point?  He even told us that it was 5 weeks to closing AFTER drywall was complete.  We are exactly 5 weeks to closing today….and drywall started TODAY!

OOOOOH, and one more thing.  We did receive our official letter about our new home orientation and closing….our new home orientation is scheduled for February 19th and closing for the 20th.   Isn’t that too close?  What if we see things during our new home orientation?  They will have no time to fix things before we close.  I emailed our closing person and they said they would see if they can move the orientation back, but it’s pretty much set in stone. 

Wow, I told you this would be long!